    Construction of electrical substation on 150 kV to Kirovsk for JSC Apatit

    JSC Apatit
    2016

    Results

    Project description

    On November 30, 2015 employees of SPBEC put into service the 150 kV new electrical substation for JSC Apatit.

    The necessity of construction of new substation was caused by the carried-out large-scale reconstruction of "The joint Kirov mine". Capacity of object increased and energy consumption respectively grew.

    It appeared capacities of the existing substations of Kirovsky district of power supply networks of JSC Apatit insufficiently for ensuring the growing energy consumption of a mining complex of mine.

    The active phase of construction of substation "Kirovski" began in July, 2014

    Work flow


     • Design
     • Preparation of a platform of construction
     • Earthwork
     • Works of a zero cycle
     • Works are higher than a zero cycle
     • Engineering networks
     • Construction of a cable platform from the existing PS-352 to new PS 150 "Kirovski"
     • Electric installation work
     • Construction VL-150kv from PS-73 to new PS 150 "Kirovski"
     • Balancing and commissioning on all equipment is carried out